Report Name: Contract Progress Report
Project: 201701: End- to- End Contract- Workforce Tracking and Reporting and all sub- projects.
Period Covered: Current Real- Time Data
Requested by: Procurement Organization - Demo Biz
Run Date: February 21, 2018 14:09:46 CST
Project: 201701: End- to- End Contract- Workforce Tracking and Reporting
Powered by ePrismSoft
Contract #
|
Name
|
Project
|
Prime/ Sub
|
Contract/ Payments
|
Status
|
Awarder/ Awardee
|
Documents
|
Intv/ Hire
|
Jobs/ Hours
|
|
Universal Multi- Use Sports Complex
|
201701: End- to- End Contract- Workforce Tracking and Reporting
|
Direct Non- Prime Contract
|
$15,000,000.00
-------
$2,000,000.00
|
Awarded Non- Certified
|
Procurement Organization - Demo Biz
-------
ABC Prime Road Construction
|
|
|
82
------- 2797
|
|
Joe White & Co Universal Multi- Use Sports Complex
|
Universal Multi- Use Sports Complex
|
Subcontract of
#36937 Universal Multi- Use Sports Complex
|
$3,500,000.00
-------
$1,500,000.00
|
Awarded Non- Certified
|
ABC Prime Road Construction
-------
Joe White and Co
|
|
|
13
------- 624
|
|
Minority Prime Universal Multi- Use Sports Complex
|
Universal Multi- Use Sports Complex
|
Subcontract of
#36937 Universal Multi- Use Sports Complex
|
$1,500,000.00
-------
$1,000,000.00
|
Awarded Certified
|
ABC Prime Road Construction
-------
Jamal Construction Demo Account
|
|
|
38
------- 1223
|
|
XYZ Concrete Universal Multi- Use Sports Complex
|
Universal Multi- Use Sports Complex
|
Subcontract of
#36937 Universal Multi- Use Sports Complex
|
$2,500,000.00
-------
$1,200,000.00
|
Awarded Non- Certified
|
ABC Prime Road Construction
-------
XYZ Concrete Co
|
|
|
22
------- 640
|
|
XYZ Concrete Minority Prime Universal Multi- Use Sports Complex
|
Universal Multi- Use Sports Complex
|
Subcontract of
#36939 Minority Prime Universal Multi- Use Sports Complex
|
$500,000.00
-------
$250,000.00
|
Awarded Non- Certified
|
Minority Prime Contractor & Co - Demo Biz
-------
XYZ Concrete Co
|
|
|
22
------- 640
|
|
Expo- Joe White & Co Universal Multi- Use Sports Complex
|
Universal Multi- Use Sports Complex
|
Subcontract of
#36938 Joe White & Co Universal Multi- Use Sports Complex
|
$250,000.00
-------
$100,000.00
|
Awarded Certified
|
Joe White and Co
-------
Ekpo & Sons - Demo Biz
|
|
|
18
------- 524
|
|
ABC Concrete- Joe White & Co Universal Multi- Use Sports Complex
|
Universal Multi- Use Sports Complex
|
Subcontract of
#36938 Joe White & Co Universal Multi- Use Sports Complex
|
$750,000.00
-------
$350,000.00
|
Awarded Non- Certified
|
Joe White and Co
-------
ABC Concrete Co
|
|
|
26
------- 732
|
|
UMTEC- XYZ Concrete Universal Multi- Use Sports Complex
|
Universal Multi- Use Sports Complex
|
Subcontract of
#36940 XYZ
Concrete Universal Multi- Use Sports Complex
|
$450,000.00
-------
$200,000.00
|
Awarded Certified
|
XYZ Concrete Co
------- UNIVERSAL MICRO TECHNOLOGIES
|
|
|
12
------- 343
|
|
UMTEC- ABC Concrete- Joe White & Co Universal Multi- Use Sports Complex
|
Universal Multi- Use Sports Complex
|
Subcontract of
#36943 ABC
Concrete- Joe White & Co Universal Multi- Use Sports Complex
|
$150,000.00
-------
$50,000.00
|
Awarded Certified
|
ABC Concrete Co
------- UNIVERSAL MICRO TECHNOLOGIES
|
|
|
12
------- 343
|
----- Progress Metrics -----
There are 3 certified subcontractors and 0 recipients of documents, of which 0 received follow- ups. There is $15,000,000.00 in prime/ direct contracts, of which:
$1,850,000.00 (12.33%) was awarded to certified subcontractors
$5,650,000.00 (37.67%) was awarded to non- certified subcontractors
$7,500,000.00 (50.00%) was the total awarded to subcontractors
$7,500,000.00 (50.00%) will be self- performed by the prime contractor.
$3,700,000.00 (24.67%) was paid out to contractors, indicating 24.67% contract completion.
Goal Information:
Enterprise Level
Goal
|
Contract Planned Value
|
Actual Value
|
% of Plan
|
% of Actual
|
10.00% US - MBE
|
$1,250,000.00
|
$850,000.00
|
8.33%
|
5.67%
|
5.00% US - WBE
|
$600,000.00
|
$250,000.00
|
4.00%
|
1.67%
|
10.00% US - Section 3
|
$1,600,000.00
|
$1,000,000.00
|
10.67%
|
6.67%
|
Contract Totals
|
$15,000,000.00
|
$2,000,000.00
|
100.00%
|
13.33%
|
Labor Utilization
Goal
|
Labor Hours
|
Percent of Total
|
18.00% Minority Workforce
|
3,073.00
|
39.07%
|
3.00% Female Workforce
|
2,736.00
|
34.78%
|
30.00% New Hire Section 3 Resident Workforce
|
No Data
|
|
Non Minority/ Female
|
3,385.00
|
43.03%
|
Total Contract Hours
|
7,866.00
|
100%
|
Demographic Statistics:
0 (0.00%) were Unspecified
2 (66.67%) were African American
0 (0.00%) were Caucasian
0 (0.00%) were Native American
0 (0.00%) were Asian
1 (33.33%) were Asian Pacific
0 (0.00%) were Hispanic
0 (0.00%) were Latin American
0 (0.00%) were Subcontinent Asian
0 (0.00%) were Other
0 (0.00%) had unspecified gender, 3 (100.00%) were male- owned, 0 (0.00%) were female- owned.
Certification Statistics:
0 (33.33%) hold OR - ESB certification.
3 (100.00%) hold US - DBE certification.
2 (66.67%) hold US - MBE certification.
3 (100.00%) hold US - PreQual certification. 2 (66.67%) hold US - Section 3 certification. 1 (33.33%) hold US - WBE certification.
Range Statistics:
Distance (Miles)
|
< 10
|
10-19
|
20-29
|
30-39
|
40-49
|
50-59
|
60-69
|
70-79
|
80-89
|
90-99
|
> 100
|
Count
|
3
(100.00%)
|
0
(0.00%)
|
0
(0.00%)
|
0
(0.00%)
|
0
(0.00%)
|
0
(0.00%)
|
0
(0.00%)
|
0
(0.00%)
|
0
(0.00%)
|
0
(0.00%)
|
0